A charterer is unable to complete the loading of a vessel during the laydays specified in the charter party. Under these circumstances,the ______.

A.charterer must pay dispatch money

B.effective period of the charter is extended

C.vessel operator can collect demurrage

D.ship is authorized extra time to discharge the cargo

正确答案是C